| I am pretty good with MS Project, but want to do something different...  Instead of having a fixed start date, end date, etc...  I want to just have a relative set of dates.  So, instead of starting Feb 09, 2005 (for example), I want to just say DAY 1.
 I need to make a general schedule for a bid, but don't want dates on it since I have no idea when this will really start.  I tried to fudge the date format so it only shows week#/day# but that doesn't help, since this project would be more than 1 year and resorts back to week1 each January I have on there.
 
 Any ideas?  Thanks!
 |